ImplementationsPre Planning

Pre Planning


TasksTime (BD)Stakeholders
Implementation methodology overview1-2Project team, senior management at client, investment teams
Aladdin Risk/WPV overview1-2Project team, senior management at client, investment teams
Key dates finalize minimum requirement
1. Receive first of data in Aladdin friendly file format - 6 weeks
2. Produce Early Look 4 weeks
3. Produce Early Look refresh 4 weeks
4. Silent parallel 6 weeks
5. Performance roll-out 2-3 weeks
2-3Project team
Project team finalize and resourcing requests for internal teams2-3Project team
Contract signed and ready to beginContract dependantProject team
Prospect readiness doc2-3BizDev
Special requirements:
Identify high priority items with contractual development is any
2-3 weeksBizDev, Implementation team