Identify all Custodian and data sources1Custodian/Client IT, Project team
Identify frequency of files from all custodian2-3Custodian/Client IT, Project team
Identify daily v month-end file requirements1Custodian/Client IT, Project team
Identify key contacts and escalation metric for all custodian/data sources2-3Custodian/Client IT, Project team
Set up weekly check-in with all custodians/data sources1Custodian/Client IT, Project team
Decide on the pos table setup for portfolios2-3Custodian/Client IT, Project team
Send Aladdin file formats to all custodian/data sources1Custodian/Client IT, Project team
Walkthrough session with Internal data team to go through each file and requirements1Custodian/Client IT, Project team
SFTP setup across custodian and testing7-8Custodian/Client IT, Project team, BLK implementation team
Receive draft files from custodian15-20Custodian/Client IT, Project team
BRS feedback on draft files5-8Custodian/Client IT, Project team
One-time interface file delivery for Early Look5-8Custodian/Client IT, Project team
Loading Early Look interface files3-5Project team
Security Master data feedback20-25Project team
Daily interface file delivery setup5-7Custodian/Client IT, Project team
Security Master reconciliation5Project team